| Province | Subbasin | % |
|---|---|---|
| Middle Snake | Owyhee | 100.00% |
| Previous: | Next: |
|---|---|
| 91171: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - WILSON 101 |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | A: 119. Project administration | 09/30/2024 | ||
| Complete Environmental Compliance Documentation | B: 165. Satisfy environmental compliance requirements. | 09/30/2024 | ||
| Beaver dam analogs | C: 29. Construct beaver dam analog | 09/30/2024 | 06/30/2024 | |
| Prevent Trespass | D: 26. Prevent trespass on property | 09/30/2024 | ||
| Photo point monitoring report | E: 115. Conduct Photo Point Monitoring | 09/30/2024 | ||
| public outreach | F: 99. Public Outreach | 09/30/2024 | 05/28/2024 | |
| Implement vegetation management activities | G: 198. Implement NRCS Vegetation Management Plan on Baker Parcel | 09/30/2024 | ||
| Complete vegetation management activities. | H: 198. Implement NRCS Vegetation Management Plan on Ratliff Parcel | 09/30/2024 | ||
| Complete vegetation Management | I: 198. Implement NRCS Vegetation Management Plan on McGinnes Parcel | 09/30/2024 | ||
| Complete vegetation management | J: 198. Implement NRCS Vegetation Management Plan on Home Parcel | 09/30/2024 | ||
| complete vegetation Monitoring | K: 198. Implement NRCS Vegetation Management Plan on Bend Parcel | 09/30/2024 | ||
| Complete vegetation management | L: 198. Implement NRCS Vegetation Management Plan on Angell Parcel | 09/30/2024 | ||
| Benefit/Income/Spending Report | M: 194. Documentation of income-producing activities on Wilson/101 Ranch | 09/30/2024 | ||
| Maintain Buildings and Structures | N: 186. Maintain structures, facilities and property | 09/30/2024 | ||
| Maintain structures and stream. | O: 186. Maintain Fences/Water Developments/Diversions | 09/30/2024 | ||
| Weed management strategy. | P: 115. Finalize Land Management Plan including an update of weed management strategy. | 09/30/2024 | ||
| Completed Annual Report | R: 132. Submit Progress Report for the period (10/1/2022 to 9/30/2023) | 09/30/2024 | ||
| Culvert replaced | S: 208. Replace culvert. | 09/30/2024 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Project administration | |||||||
| B | 165 | Satisfy environmental compliance requirements. | |||||||
| C | 29 | Construct beaver dam analog | |||||||
| D | 26 | Prevent trespass on property | |||||||
| E | 115 | Conduct Photo Point Monitoring | 08/30/2023 | ||||||
| F | 99 | Public Outreach | |||||||
| G | 198 | Implement NRCS Vegetation Management Plan on Baker Parcel | 08/30/2023 | ||||||
| H | 198 | Implement NRCS Vegetation Management Plan on Ratliff Parcel | 08/30/2023 | ||||||
| I | 198 | Implement NRCS Vegetation Management Plan on McGinnes Parcel | 08/30/2023 | ||||||
| J | 198 | Implement NRCS Vegetation Management Plan on Home Parcel | 08/30/2023 | ||||||
| K | 198 | Implement NRCS Vegetation Management Plan on Bend Parcel | 08/30/2023 | ||||||
| L | 198 | Implement NRCS Vegetation Management Plan on Angell Parcel | 08/30/2023 | ||||||
| M | 194 | Documentation of income-producing activities on Wilson/101 Ranch | 08/30/2023 | ||||||
| N | 186 | Maintain structures, facilities and property | 08/30/2023 | ||||||
| O | 186 | Maintain Fences/Water Developments/Diversions | 08/30/2023 | ||||||
| P | 115 | Finalize Land Management Plan including an update of weed management strategy. | 08/30/2023 | ||||||
| Q | 185 | Periodic Status Reports for BPA | |||||||
| R | 132 | Submit Progress Report for the period (10/1/2022 to 9/30/2023) | |||||||
| S | 208 | Replace culvert. |